Track Resurfacing Progress |
The resurfacing of the track at Hagenaeuer's Reserve was finally completed on Tuesday 2nd June 2008 and the track handed back to the club ready to once again be used for training and competition.
Due to a number of factors beyond the Club's control, including works at other grounds creating conflicting demands for the Contractor's resources, machinery breakdowns and wet weather, the works were over a month late in being completed.
However, the completed track with the additional 2 lanes on the front straight and new dual long jump / triple jump runup looks fantastic so will be worth the long wait and inconvenience.
Works commenced on resurfacing of the track on Tuesday 4th December, after more than 18 months of preparing grant submissions, lobbying Council for support, negotiating various parties to determine priorities for redevelopment works, consulting with the Council and design consultant during the design phase and then lobbying Councillors to support the project. A comprehensive set of progress photos of the resurfacing works are included below:
100 m start and long jump pit | 100 m start - inside lanes | |
Top Bend | 200 m start | |
Back Straight | 1500 m start | |
Front Straight | Finish Line | |
Southern Long Jump pit and runup | Northern Long Jump pit and runup |
Back Straight line markings |
Front Straight line markings |
Sprayed Edges of Bottom Bend with Red Surface | Red Edges of Bottom Bend | |
Red Edges of Finish Area | Black Rubber on Front Straight | |
Pole Vault Take-off Red Surface | North Pole Vault Pit Red Surface |
Black Rubber Surface on Bottom Bend | Newly laid black rubber on Bottom Bend |
Pole Vault Runup New Concrete Edge Strips | Pole Vault Runup New Concrete Edge Strips | |
Landscaping around Pole Vault Runup | Long Jump Runup with Rubber Surfacing | |
View across Bottom Bend | View across Finish Line | |
Applying Rubber Surfacing to Back Straight | Black Rubber Surface near 1500 Start |
Demolished Pole Vault Runup | Demolished Runup at Southern Pole Vault Pit | |
Track Material Stored in Bags | Front Straight Ready for Application of Rubber |
New bitumen on bottom bend | New bitumen on new lanes in front straight | |
Northern long jump pit and new bitumen on runup | New jump board inserts |
New bitumen on bottom straight | Bitumen patches near finish line | |
New bitumen on long jump runup | New long jump pit and runup |
Bitumen Profiled on Bottom Bend | Finish Line Area ready for asphalt | |
Widened Front Straight ready for asphalt | Sand added to jump pits |
Northern Jump Pit Concrete Works | New Concrete Edging at 100 m Start | |
South Jump Pit and Track Extension | New Concrete Strip Between Track and Jump Pits |
Spoon Drain around new track |
Long Jump Concrete Edging |
Finish Line and Bottom Bend |
Bottom Bend |
|
Finish Line and Infield |
Long Jump and Front Straight |
Track Stripped from Bottom Bend |
Finsh Line |
|
Long Jump Sub Base |
Front Straight |
Lane 9 and 10 Sub Base |
Trench for Electrical Conduit |
|
Long Jump Sub Grade |
Long Jump Sub Base |
Lane 9 and 10 Excavation |
||